MASSACHUSETTS · THRESHOLDS & STATUTES
The dollar lines Massachusetts procurement law draws.
Three statutes run Massachusetts public purchasing: c.30B (the Uniform Procurement Act, municipal supplies and services: quotes at $10K, sealed bids over $50K), c.149 §§44A-44J (public buildings: full filed-sub-bid competition at $150K), and c.30 §39M (public works: publicly opened bids over $50K with a 5% bid deposit). Every figure links its statute page on malegislature.gov. This page is informational, not legal advice.
M.G.L. c.30B §4
Supplies & services: written quotations band
$10,000
The Uniform Procurement Act governs every municipal (and many district) purchase of supplies and services. Between $10,000 and $50,000 the procurement officer must seek at least three written quotations and award to the lowest responsible quote; below $10,000, sound business practices suffice. Section 5 governs sealed bids above $50,000 and §6 governs RFPs.
For vendors: the $10K-$50K quote band is where fast, complete quotes win; over $50K watch COMMBUYS and the local paper for the IFB/RFP.
malegislature.gov/.../PartI/TitleIII/Chapter30B/Section4C.30B §4 and c.149 §44A were retrieved verbatim.
M.G.L. c.30B §5 / §6
Supplies & services: sealed bidding / proposals line
$50,000
Above the line, a governmental body must advertise (newspaper of general circulation and COMMBUYS) and run a formal IFB, or an RFP under §6 when factors beyond price matter. Award under an IFB goes to the lowest responsible and responsive bidder.
For vendors: above $50K there is no informal path; COMMBUYS registration and bid-alert codes matter.
malegislature.gov/.../PartI/TitleIII/Chapter30B/Section5C.30B §4 and c.149 §44A were retrieved verbatim.
M.G.L. c.149 §44A(2)
Public buildings: small-project bands
$10,000
Public building work has its own statute. Small building projects under $50,000 follow the written-response procedure; using a statewide-contract vendor or an approved blanket-contract vendor list can satisfy the notification requirement.
For building trades: getting onto OSD statewide contracts and municipal blanket vendor lists removes the public-notification hurdle for small jobs.
malegislature.gov/.../PartI/TitleXXI/Chapter149/Section44AM.G.L. c.149 §§44A-44J
Public buildings: filed sub-bid line
$150,000
At or above $150,000 a public building project requires advertised general bids AND filed sub-bids in designated trades (masonry, electrical, plumbing, HVAC, and others per §44F), with award to the lowest responsible and eligible bidder. Between $50,000 and $150,000 the simpler §39M procedure applies.
For subs: filed sub-bids go directly to the awarding authority, not the GC; prime certification via DCAMM gates state building work over $150K.
malegislature.gov/.../PartI/TitleXXI/Chapter149/Section44ASecondary cross-check: AGC/OG guidance.
M.G.L. c.30 §39M
Public works (non-building): competitive bids line
$50,000
Horizontal construction (roads, bridges, sewers, site work) follows §39M rather than c.149: no filed sub-bids, but public opening, a 5% bid deposit, OSHA 10-hour certification for site workers, and a payment-bond obligation via c.149 §29.
For heavy-civil contractors: the 5% bid deposit and OSHA-10 certifications are checked at bid time; have both ready.
malegislature.gov/.../PartI/TitleIII/Chapter30/Section39MText is also cross-checked against the Office of the Inspector General public-works guidance and c.149 §44A cross-reference.
M.G.L. c.7C §§44-58
Designer selection (A/E services)
Architects, engineers, and related design professionals on public building projects are selected on qualifications through the designer selection law, not low bid: municipalities advertise, evaluate, and negotiate. COMMBUYS and the Central Register carry the announcements.
For A/E firms: the SOQ decides the shortlist; price is negotiated after selection.
malegislature.gov/.../PartI/TitleII/Chapter7C/Section51Framework also cross-checked against Inspector General and mass.gov guidance.
M.G.L. c.149 §29
Payment bonds on public construction
100%
Massachusetts requires payment-bond security on public construction, and the §39M bid deposit is 5% of the bid value. Massachusetts also has a prevailing-wage law (c.149 §§26-27H) applying to public construction, unlike states without one; Davis-Bacon applies to federally assisted work.
For contractors: confirm bonding capacity and review the DLS wage schedule before pricing public work.
malegislature.gov/.../PartI/TitleXXI/Chapter149/Section29C.30B §4 and c.149 §44A were retrieved verbatim.
Where these portals live: verification-labeled Massachusetts procurement sources and the 14-county local explorer.